Get Familiar With CAPM, Third Edition
By Certification Magazine —
1 | 2 |
References:
A Guide to the Project Management Body of Knowledge, Third Edition (PMBOK Guides): Project Cost Management - 7.3.2 Cost Control: Tools and Techniques
A Guide to the Project Management Body of Knowledge, Third Edition (PMBOK Guides): Glossary - Schedule Performance Index (SPI)
Objective: Project closing.
Sub-objective: Close project.
Single answer, multiple choice
Which of the following is NOT an input of the Close Project process?
A. Contract documentation.
B. Project management plan.
C. Formal acceptance of the final product, service or result.
D. Organizational process assets.
Answer:
C. Formal acceptance of the final product, service or result.
Tutorial:
The formal acceptance of the final product, service or result is not an input of the Close Project process. Formal acceptance is an output of the Close Project process.
The inputs of the Close Project process are the project management plan, contract documentation, enterprise environmental factors, organizational process assets, work performance information and deliverables.
Reference:
A Guide to the Project Management Body of Knowledge, Third Edition (PMBOK Guides): Project Integration Management - 4.7 Close Project
1 | 2 |



