Learn About Project Management Professional Exam
By Certification Magazine —
1 | 2 |
Reference:
Develop Project Team: Tools and Techniques
PMBOK guide, 4th Edition
Chapter 9
Objective: Project integration management.
Sub-objective: Close project.
Single answer, multiple-choice
What should you update during the close project or phase process?
A. Organizational process assets.
B. Work performance information.
C. Work breakdown structure (WBS).
D. Activity list.
Answer:
A
Tutorial:
You should update the organizational process assets during the close project or phase process. Making these updates is one of the outputs of this process.
You do not update the work performance information during the close project or phase process. It is an output of the direct and manage project process.
You do not update the WBS during the close project or phase process.
You do not update the activity list during the close project or phase process.
Reference:
Close Project or Phase
PMBOK guide, 4th Edition
Chapter 4